Rabbs Bayou Flood and Drainage Improvements

Rosenberg

Summary

A $51,981.76 change order keeps the Rabbs Bayou flood and drainage mitigation project moving — 99% paid for by federal CDBG-MIT grant funds.

At a glance

Total mentions
1
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 15, 2026.

Impact analysis

💰Financial impact

City's share of the $51,981.76 change order is roughly 1% of the cost; the rest is federal grant money.

✅Who benefits

Residents in the Rabbs Bayou drainage area get improved flood protection.

Mentions & discussions (1)